Four Years, Three Budgets, One Abandoned Promise: Inside Plateau’s Unfinished Mangu Bye Pass

Published

on

Spread the love

Bulmun Dakwal

Standing on what was meant to become the Mangu Bye Pass, Elisha Gutuwas points not to a busy highway bustling with heavy duty trucks, but to patches of maize and millet now growing where bulldozers once worked.

The land chosen to ease congestion in Mangu town has slowly returned to its original purpose. Thick grasses now cover long stretches of the abandoned route. In some places, the graded path has almost disappeared entirely beneath vegetation. Nearby, an unfinished bridge stretches halfway across a stream before ending abruptly, its exposed concrete pillars serving as a silent reminder of another government promise left unfulfilled.

For the people of Daika and surrounding communities, the project no longer represents hope. It has become a symbol of years of waiting.

“As you can see, the people got tired of waiting for the government and are already farming on the supposed road,” Mr Gutuwas told SecretsReporters during a visit to the project site.

“Since the government graded the road in 2021, they have not come back to continue any work here.”

His frustration mirrors that of many residents whose expectations were raised when construction equipment first arrived.

The Mangu Bye Pass was conceived as a strategic infrastructure project designed to divert vehicles, trailers and other heavy duty trucks away from Mangu township, easing congestion and reducing the pressure on the existing road network. Residents believed the project would shorten travel time, improve road safety and stimulate economic activities between Mangu and other neighbouring communities.

Instead, what remains is a half executed project that has continued to consume space in government budgets while making little visible progress in reality.

An analysis of Plateau State budget documents reviewed by Secrets Reporters shows that the bypass has appeared repeatedly in successive budgets over the last four years, raising questions about the pace of implementation and the management of public infrastructure projects.

The journey began in 2021, when the Plateau State Government awarded a 541 million naira contract through the Ministry of Works for the construction of the Mangu Bye Pass, making resident’s expectations high. High duty tractors and equipment arrived, portions of the route were graded and work commenced on a bridge intended to connect Sabon Gari to Bwai.

However, before long, construction slowed down and eventually stopped. Rather than disappearing from government plans, the project resurfaced in the 2023 approved budget, where another 150 million naira was allocated under the road construction programe for the “Construction of Mangu Bye Pass.” The fresh allocation suggested that government intended to continue work on the road after the initial contract stalled.

Yet budget implementation records reviewed by SecretsReporters indicate that despite the appropriation, no meaningful progress was recorded during the implementation period. For residents who had watched construction halt years earlier, the additional allocation brought renewed optimism that quickly faded as the project site remained largely deserted.

Two years later, the bypass again found its way into government spending plans. This time, the 2025 budget described it as the “Construction of 13KM Mangu Bye Pass” and significantly increased the allocation to 1 billion naira more than six times the amount provided in 2023. On paper, the increased budget felt like a renewed commitment to completing the long-delayed project. However, budget implementation records tell a different story.

Documents show that out of the 1 billion naira allocated for the bypass, only 60 million naira had been released during the reporting period, representing barely six percent of the approved allocation. The figures raise fresh concerns about whether the repeated budgetary allocations are translating into meaningful construction activity on the ground.

Each new budget announcement raises hopes that construction will finally resume. Each passing year without substantial progress deepens public scepticism.

When SecretsReporters visited the project corridor, the signs of abandonment were unmistakable.

The road that was once graded has become overgrown with weeds. In several sections, grasses have reclaimed the graded surface, making portions of the proposed bypass almost impossible to identify. The unfinished bridge leading towards Bwai remains suspended in time, preventing cars from using what should have become a major alternative route into the community.

For commercial driver Polycap Nanjwan, the abandoned project represents more than wasted public funds. It represents years of unrealised expectations.

“I remember when I saw people grading the road,” he recalled.

“My colleagues and I were very happy because we believed that once the bypass was completed, all the heavy trucks and buses would use that road. Traffic inside Mangu town would reduce and movement would become easier.”

Instead, he said, the construction stopped almost as quickly as it began.
“They came, gave us hope and left. It’s been over three years and we have not seen anybody again. If you go through the road now, you’ll see that it has been covered by grasses.”

For Martha Ambrose, the abandoned bridge turned what should have been a shorter journey into an unexpected detour.

She recalled travelling with a family member on a motorcycle after being told they could access Bwai through the newly constructed bypass.

Instead, they encountered an incomplete bridge that made the route impassable.

“We really thought the road had been fixed according to what people told us,” She said.

“But when we got there, we saw a huge gap created by the river and unfinished bridge pillars. We had to turn back and use the old Mangu Bwai road.”

Perhaps the greatest burden has been borne by farmers whose livelihoods were directly affected by the project.

Among them is Polycap Datugum, whose farmland lies along the proposed alignment.

According to him, government officials acquired part of his land when construction commenced, assuring affected residents that the sacrifice would serve the public interest. Years later, he says, neither the promised road nor compensation was given to him.

“My land was divided into two, and this place where you’re standing used to be part of my farm,” he said.
“We believed we would receive some form of compensation, but till today we have not heard anything.”
He paused before adding quietly “The government has not completed the road, and we cannot even farm on the part they took from us. We are hoping that the present administration will continue from where the previous government stopped.”

For accountability advocates, the Mangu Bye Pass illustrates a broader concern about public infrastructure delivery in Nigeria: projects are often announced with fanfare, repeatedly budgeted, and sometimes partially executed, yet communities continue to wait years for the promised benefits. In Mangu, the story is no longer just about an unfinished road. It is about residents who have watched budgets come and go while the bypass remains largely a promise on paper. Each new appropriation has rekindled hope that construction will resume, but on the ground, the overgrown road and abandoned bridge tell a different story.

Promises Revisited, Questions Remain
Four years after the Mangu Bye Pass was first conceived, there appears to be renewed hope for residents.

On July 22, 2026, Plateau State Governor Caleb Mutfwang flagged off the construction of a 19.7-kilometre Mangu Bypass, describing it as a strategic investment that would decongest Mangu town, improve connectivity and transform the area into a major economic hub. According to the governor, his administration reviewed the project inherited from the previous government and expanded its scope from 14 kilometres to 19.7 kilometres, incorporating three major bridges, reinforced stone base, improved drainage systems and engineering standards expected to give the road a lifespan of more than 20 years.
The announcement has once again reignited hope among residents who have spent years waiting for the bypass to become a reality.

For commercial drivers, it promises relief from the daily traffic that have continued to plague Mangu town. For farmers, it offers the possibility of easier access to markets. For businesses, it could open new economic opportunities and reduce travel time for goods moving across Plateau State.

But optimism is accompanied by caution. This is not the first time the people of Mangu have been promised a bypass. They have watched contractors move to site before, bulldozers clear sections of the proposed route, watched bridge pillars rise from the river and also watched construction stop.

To many residents, the concern is no longer about announcements but it is about execution. Will this latest groundbreaking ceremony finally deliver the bypass that has existed on paper for years? Will the promises make in 2026 succeed where previous commitments fell short or will the Mangu Bye Pass return once again to future budget documents while the unfinished bridge, the overgrown road corridor and the reclaimed farmlands continue to tell a different story?

Until then, many residents say they have learnt to greet every new promise with cautious optimism.
Because in Mangu, history has taught them that a budget allocation is not a completed road, and a groundbreaking ceremony is not a guarantee that the journey will finally reach its destination.

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Latest

Corruption16 minutes ago

N10 Billion Paid To Six Months Old Company And Four Ghost Companies: Inside Fmr Minister Wale Edun, NRS Chairman Zaach Adedeji And Perm. Sec Lydia Jafiya’s PCNGI Contract Heist

Spread the loveSecretsReporters The Presidential CNG Initiative (PCNGI) was sold to Nigerians as a lifeline, a federal programme meant to...

Corruption18 hours ago

Private Business Claims Linked to Permanent Secretary John Chidiebere Ezeamama in Violation of Code of Conduct for Civil Servants

Spread the loveSecrets Reporters   SecretsReporters has reviewed public records concerning Dr. John Chidiebere Ezeamama, the Permanent Secretary of the...

Corruption1 day ago

N1.63 Billion Web of Questionable Spending Uncovered at Nigeria’s Peace Institute

Spread the loveBy Secrets Reporters SecretsReporters has obtained internal records exposing a pattern of financial irregularities at the Institute for...

Politics2 days ago

Political Witch Hunting: Tinubu’s Tax Man, Zaach Adedeji Begins Audit Of Irvin Global One Day After Peter Visited MD

Spread the loveSecrets Reporters The Nigeria Revenue Service (NRS) has commenced a full-scale tax audit of Irvin Global and Investment...

Corruption2 days ago

Against CCB Law, NSIA Boss Aminu Umar-Sadiq Runs Various Private Companies

Spread the loveSecrets Reporters Corporate Affairs Commission records obtained by SecretsReporters have linked the Managing Director and Chief Executive Officer...

Contract Fraud2 days ago

Olodo Uprising: How MDGIF Boss Oluwole Adama Paid N326 Million To Take Advise Yet No Advise Was Given

Spread the loveSecrets Reporters The Executive Director of Midstream and Downstream Gas Infrastructure Fund (MDGIF), Mr Oluwoke Adama is in...

Corruption3 days ago

University of Ilorin, Kwara State: How ₦1.27bn in IGR and PAYE Remittances Went Unaccounted For

Spread the loveSecrets Reporters    The University of Ilorin, Kwara State, has come under the radar of SecretsReporters over the...

Corruption3 days ago

FUT Minna Records N21.3m in Financial Irregularities Under 2019 Review

Spread the loveSecrets Reporters   A review of the financial records of the Federal University of Technology, Minna, Niger State,...

Corruption3 days ago

Exclusive: Nyesom Wike’s Ally, Alabo George Whose DG BCDA Purchase Luxurious Mansion Worth $878,659

Spread the loveDocuments have exposed the purchase of a luxurious mansion by Dakorinama Alabo George, the Director-General of the Border...

Contract Fraud3 days ago

EXCLUSIVE: HYPREP Coordinator, Zabbey Diverts Billions Of Ogoni Cleanup Funds To Personal Company

Spread the loveSecrets Reporters Corporate records and official project documents have raised fresh conflict of interest questions over the corporate...

Corruption4 days ago

FAAN Audit Report:  $172,328 Foreign Trips Undertaken Without Appropriate Approval

Spread the loveSecrets Reporters An audit report has uncovered foreign travel expenses amounting to $172,328 allegedly incurred by the Federal...

Corruption4 days ago

Exclusive: Nigeria’s Defence Minister Daughter Matawalle Firdausi Acquires $329,402 Luxurious Mansion in US

Spread the loveSecrets Reporters   Documents sighted by SecretsReporters have exposed the luxury lifestyle and acquisition of a mansion by...

General News5 days ago

Update: NNPC ANTAN Director Moses Tsado Declared US Mortgage Home in CCB Form

Spread the loveSecrets Reporters Following an exclusive report by SecretsReporters on alleged purchased of a US property by the Tsado...

Contract Fraud5 days ago

FAAN Audit Report: N72.3m Contract Splitting Allegedly Used To Bypass Tenders Board

Spread the loveSecrets Reporters An audit report has uncovered alleged contract splitting amounting to N72,314,050 at the Federal Airports Authority...

Corruption5 days ago

Exclusive: How Senator Joel Onowakpor Purchased $2.6m US Mansion While Serving As FIRS South South Coordinator

Spread the loveSecrets Reporters A six-bedroom, eight-bathroom single-family residence at 11507 Bistro Lane in the Royal Oaks Country Club subdivision...

Corruption6 days ago

FAAN Spends N199.6m on Staff Professional Subscriptions Despite 2009 Government Directive

Spread the loveSecrets Reporters The Federal Airports Authority of Nigeria (FAAN) spent N199,605,849.86 on professional subscriptions and certifications for its...

Corruption6 days ago

Nigeria Embassy in Equatorial Guinea: $287,906.60 in Unutilised Funds, Four Unserviceable Vehicles Uncovered

Spread the loveSecrets Reporters   Public funds allocated to Nigeria’s diplomatic missions abroad are meant to keep its buildings functional...

Corruption6 days ago

Audit Questions N49.98m Payment for Computers, Laptops Supplied to Four Northern Locations

Spread the love Secrets Reporters An audit of expenditure of Federal Airport Authority of Nigeria (FAAN), has raised concerns over the...

General News7 days ago

We Spend Private Money To Run NNPCL Not Public Funds, GCEO Ojulari’s Administration Tells Nigerians Despite Appointed By FG

Spread the loveSecrets Reporters The Nigerian National Petroleum Company Limited (NNPC Limited), under the leadership of its Group Chief Executive...

World News7 days ago

Washington Post Ordered to Reinstate Columnist Fired Over Charlie Kirk Posts

Spread the loveSecrets Reporters The Washington Post has been ordered to reinstate columnist Karen Attiah after an arbitrator ruled that...


Support Independent News